North TexasTop story
Westlake approves the data center agreement near Keller after months of legal fights
The planned data center campus sits close to Keller homes
- 88 acres
- planned for the campus
- 1.1 million
- square feet across four buildings
- 500 feet
- from the backyards of Keller residents
- $5 million
- a year for Westlake over the first 10 years
Sources: NBC 5 Dallas-Fort Worth, Fort Worth Report
If you've followed the fight over the data center on the Keller-Westlake line, it just cleared a big hurdle. Westlake's Town Council approved a development agreement Thursday night, Nov. 12, with PowerHouse Data Centers. The vote was 5-1, and the campus would sit near U.S. 377 and Westport Parkway.
The deal follows a legal dispute with Keller that ended in a $1.9 million settlement. Council members also unanimously approved a settlement agreement among Westlake, Keller, the developer and residents of the adjacent homes.
- Settlement parties: Westlake, Keller, the developer and neighboring residents
- Keller dispute ended in a $1.9 million settlement
- Protections: noise restrictions and drainage protections for nearby homes
- Tax revenue: $7 million a year after the first 10 years
The data center deal moved from a court block to approval
- AugustThe development agreement was set for approval, but a temporary restraining order barred the council.
- Nov. 5The developer, Keller and homeowners signed a settlement.
- Nov. 12Westlake's Town Council voted 5-1 to approve the development agreement.
Sources: NBC 5 Dallas-Fort Worth, Fort Worth Report